A risk is a potential for loss or damage to an Organization from materialized threats. Risk Analysis attempts to identify all the risks and then quantify the severity of the risks.A threat as we have seen is a possible damaging event. If it occurs, it exploits vulnerability in the security of a computer based system.
----
Risk Identification
1. Software Risks:
Knowledge of the most common risks associated with Software development, and the platform you are working on.
2. Business Risks: Most common risks associated with the business using the Software
3. Testing Risks: Knowledge of the most common risks associated with Software Testing for the platform you are working on, tools being used, and test methods being applied.
4. Premature Release Risk: Ability to determine the risk associated with releasing unsatisfactory or untested Software Prodicts.
5. Risk Methods: Strategies and approaches for identifying risks or problems associated with implementing and operating information technology, products and process; assessing their likelihood, and initiating strategies to test those risks.
----
What is Schedule Risk?
In your project, you have to estimate how long it takes to complete a certain task.
You estimate that it usually takes 15 days to complete. If things go well it may take 12 days but if things go badly it may take 20 days.
In your project plan you enter 15 days against the task.
The other information, the best case estimate of 12 days and the worst case estimate of 20 days, is not entered into the project at all.
If this seems familiar, then you already go through the process of identifying uncertainty or risk. By entering only the most likely duration a great deal of additional information is lost. But with Schedule Risk this extra information is used to help produce a much more realistic project.
And you are not just limited to durations. Uncertainty in resources and costs can also be modeled in your project to produce an even greater depth and accuracy to the information available to you.
Who should use Schedule Risk Analysis?The simple answer is - anyone who manages a project! If you are running projects that are time and/or cost critical, risk analysis will help you manage your projects more effectively and help reduce the chances of your project being late and over budget.
Pertmaster is used by project planners of all levels, from those just entering into the Schedule Risk arena to the world's leading risk experts.
How easy is it to use?Very easy. You do not need to be an expert in risk and statistics to be able to use schedule risk. With normal project planning, the level of detail and complexity that you build into the project is up to you and your requirements. This is the same with Schedule Risk. Very little extra information is required as a minimum but you have the ability to provide a great deal of very specific additional information if you require it.
Pertmaster is acclaimed as being very easy to use. By simply following the tutorials and examples you will be able to incorporate risk into your project with ease. Pertmaster includes a Quick Risk (link) facility that lets you add risk to your project in seconds.
-----
What is Schedule Risk?
In your project, you have to estimate how long it takes to complete a certain task.
You estimate that it usually takes 15 days to complete. If things go well it may take 12 days but if things go badly it may take 20 days.
In your project plan you enter 15 days against the task.
The other information, the best case estimate of 12 days and the worst case estimate of 20 days, is not entered into the project at all.
If this seems familiar, then you already go through the process of identifying uncertainty or risk. By entering only the most likely duration a great deal of additional information is lost. But with Schedule Risk this extra information is used to help produce a much more realistic project.
And you are not just limited to durations. Uncertainty in resources and costs can also be modeled in your project to produce an even greater depth and accuracy to the information available to you.
Who should use Schedule Risk Analysis?The simple answer is - anyone who manages a project! If you are running projects that are time and/or cost critical, risk analysis will help you manage your projects more effectively and help reduce the chances of your project being late and over budget.
Pertmaster is used by project planners of all levels, from those just entering into the Schedule Risk arena to the world's leading risk experts.
How easy is it to use?Very easy. You do not need to be an expert in risk and statistics to be able to use schedule risk. With normal project planning, the level of detail and complexity that you build into the project is up to you and your requirements. This is the same with Schedule Risk. Very little extra information is required as a minimum but you have the ability to provide a great deal of very specific additional information if you require it.
Pertmaster is acclaimed as being very easy to use. By simply following the tutorials and examples you will be able to incorporate risk into your project with ease. Pertmaster includes a Quick Risk (link) facility that lets you add risk to your project in seconds.
--------
Risk Assessment
Risk assessment may be the most important step in the risk management process, and may also be the most difficult and prone to error. Once risks have been identified and assessed, the steps to properly deal with them are much more programmatical.
Part of the difficulty of risk management is that measurement of both of the quantities in which risk assessment is concerned can be very difficult itself. Uncertainty in the measurement is often large in both cases. Also, risk management would be simpler if a single metric could embody all of the information in the measurement. However, since two quantities are being measured, this is not possible. A risk with a large potential loss and a low probability of occurring must be treated differently than one with a low potential loss but a high likelihood of occurring. In theory both are of nearly equal priority in dealing with first, but in practice it can be very difficult to manage when faced with the scarcity of resources, especially time, in which to conduct the risk management process. Expressed mathematically,

Financial decisions, such as insurance, often express loss terms in dollars. When risk assessment is used for public health or environmental decisions, there are differences of opinions as to whether the loss can be quantified in a common metric such as dollar values or some numerical measure of quality of life. Often for public health and environmental decisions, the loss term is simply a verbal description of the outcome, such as increased cancer incidence or incidence of birth defects. In that case, the "risk" is expressed as:

If the risk estimate takes into account information on the number of individuals exposed, it is termed a "population risk" and is in units of expected increased cases per a time period. If the risk estimate does not take into account the number of individuals exposed, it is termed an "individual risk" and is in units of incidence rate per a time period. Population risks are of more use for cost/benefit analysis; individual risks are of more use for evaluating whether risks to individuals are "acceptable".
----
Risk assessment in public health
In the context of public health, risk assessment is the process of quantifying the probability of a harmful effect to individuals or populations from certain human activities. In most countries, the use of specific chemicals, or the operations of specific facilities (e.g. power plants, manufacturing plants) is not allowed unless it can be shown that they do not increase the risk of death or illness above a specific threshold. For example, the American Food and Drug Administration (FDA) regulates food safety through risk assessment. The FDA required in 1973 that cancer-causing compounds must not be present in meat at concentrations that would cause a cancer risk greater than 1 in a million lifetimes.
--------
Risk assessment in auditing
In auditing, risk assessment is a very crucial stage before accepting an audit engagement. According to ISA315 Understanding the Entity and its Environment and Assessing the Risks of Material Misstatement, "the auditor should perform risk assessment procedures to obtain an understanding of the entity and its environment, including its internal control."
The main purpose of risk assessment procedures is to help the auditor understand the audit client. Aspects like client's business nature, management structure and internal control system are good examples. The procedures will provide audit evidence relating to the auditor’s risk assessment of a material misstatement in the client’s financial statements. Then, auditor obtains initial evidence regarding the classes of transactions at the client and the operating effectiveness of the client’s internal controls.
In auditing, audit risk includes inherent risk, control risk and detection risk
--
Criticisms of quantitative risk assessment
Barry Commoner and other critics have expressed concerns that risk assessment tends to be overly quantitative and reductive. For example, they argue that risk assessments ignore qualitative differences among risks. Some charge that assessments may drop out important non-quantifiable or inaccessible information, such as variations among the classes of people exposed to hazards. O'Brien further claims that quantitative approaches divert attention from precautionary or preventative measures.
---
Risk ManagementRisk management is a structured approach to managing uncertainty through, risk assessment, developing strategies to manage it, and mitigation of risk using managerial resources.
The strategies include transferring the risk to another party, avoiding the risk, reducing the negative effect of the risk, and accepting some or all of the consequences of a particular risk.
Some traditional risk managements are focused on risks stemming from physical or legal causes (e.g. natural disasters or fires, accidents, death and lawsuits). Financial risk management, on the other hand, focuses on risks that can be managed using traded financial instruments.
Objective of risk management is to reduce different risks related to a preselected domain to the level accepted by society. It may refer to numerous types of threats caused by environment, technology, humans, organizations and politics. On the other hand it involves all means available for humans, or in particular, for a risk management entity (person, staff, organization).
---
Create a risk management plan
Select appropriate controls or countermeasures to measure each risk. Risk mitigation needs to be approved by the appropriate level of management. For example, a risk concerning the image of the organization should have top management decision behind it whereas IT management would have the authority to decide on computer virus risks.
The risk management plan should propose applicable and effective security controls for managing the risks. For example, an observed high risk of computer viruses could be mitigated by acquiring and implementing antivirus software. A good risk management plan should contain a schedule for control implementation and responsible persons for those actions.
According to ISO/IEC 27001, the stage immediately after completion of the Risk Assessment phase consists of preparing a Risk Treatment Plan, which should document the decisions about how each of the identified risks should be handled. Mitigation of risks often means selection of Security Controls, which should be documented in a Statement of Applicability, which identifies which particular control objectives and controls from the standard have been selected, and why.
-----
Implementation
Follow all of the planned methods for mitigating the effect of the risks. Purchase insurance policies for the risks that have been decided to be transferred to an insurer, avoid all risks that can be avoided without sacrificing the entity's goals, reduce others
---
Review and evaluation of the plan
Initial risk management plans will never be perfect. Practice, experience, and actual loss results will necessitate changes in the plan and contribute information to allow possible different decisions to be made in dealing with the risks being faced.
Risk analysis results and management plans should be updated periodically. There are two primary reasons for this:
- to evaluate whether the previously selected security controls are still applicable and effective, and
- to evaluate the possible risk level changes in the business environment. For example, information risks are a good example of rapidly changing business environment
------
Risk management and business continuityRisk management is simply a practice of systematically selecting cost effective approaches for minimising the effect of threat realization to the organization. All risks can never be fully avoided or mitigated simply because of financial and practical limitations. Therefore all organizations have to accept some level of residual risks. Whereas risk management tends to be preemptive, business continuity planning (BCP) was invented to deal with the consequences of realised residual risks. The necessity to have BCP in place arises because even very unlikely events will occur if given enough time. Risk management and BCP are often mistakenly seen as rivals or overlapping practices. In fact these processes are so tightly tied together that such separation seems artificial. For example, the risk management process creates important inputs for the BCP (assets, impact assessments, cost estimates etc). Risk management also proposes applicable controls for the observed risks. Therefore, risk management covers several areas that are vital for the BCP process. However, the BCP process goes beyond risk management's preemptive approach and moves on from the assumption that the disaster will realize at some point.
---
Areas of risk management
As applied to corporate finance, risk management is the technique for measuring, monitoring and controlling the financial or operational risk on a firm's balance sheet.
The Basel II framework breaks risks into market risk (price risk), credit risk and operational risk and also specifies methods for calculating capital requirements for each of these components.
Enterprise risk management In enterprise risk management, a risk is defined as a possible event or circumstance that can have negative influences on the Enterprise in question. Its impact can be on the very existence, the resources (human and capital), the products and services, or the customers of the enterprise, as well as external impacts on society, markets, or the environment. In a financial institution, enterprise risk management is normally thought of as the combination of credit risk, interest rate risk or asset liability management, market risk, and operational risk.
In the more general case, every probable risk can have a preformulated plan to deal with its possible consequences (to ensure contingency if the risk becomes a liability).
From the information above and the average cost per employee over time, or cost accrual ratio, a project manager can estimate
- the cost associated with the risk if it arises, estimated by multiplying employee costs per unit time by the estimated time lost (cost impact, C where C = cost accrual ratio * S).
- the probable increase in time associated with a risk (schedule variance due to risk, Rs where Rs = P * S):
- Sorting on this value puts the highest risks to the schedule first. This is intended to cause the greatest risks to the project to be attempted first so that risk is minimized as quickly as possible.
- This is slightly misleading as schedule variances with a large P and small S and vice versa are not equivalent. (The risk of the RMS Titanic sinking vs. the passengers' meals being served at slightly the wrong time).
- the probable increase in cost associated with a risk (cost variance due to risk, Rc where Rc = P*C = P*CAR*S = P*S*CAR)
- sorting on this value puts the highest risks to the budget first.
- see concerns about schedule variance as this is a function of it, as illustrated in the equation above.
Risk in a project or process can be due either to Special Cause Variation or Common Cause Variation and requires appropriate treatment. That is to re-iterate the concern about extremal cases not being equivalent in the list immediately above.
Risk management activities as applied to project management
In project management, risk management includes the following activities:
- Planning how risk management will be held in the particular project. Plan should include risk management tasks, responsibilities, activities and budget.
- Assigning a risk officer - a team member other than a project manager who is responsible for foreseeing potential project problems. Typical characteristic of risk officer is a healthy skepticism.
- Maintaining live project risk database. Each risk should have the following attributes: opening date, title, short description, probability and importance. Optionally a risk may have an assigned person responsible for its resolution and a date by which the risk must be resolved.
- Creating anonymous risk reporting channel. Each team member should have possibility to report risk that he foresees in the project.
- Preparing mitigation plans for risks that are chosen to be mitigated. The purpose of the mitigation plan is to describe how this particular risk will be handled – what, when, by who and how will it be done to avoid it or minimize consequences if it becomes a liability.
- Summarizing planned and faced risks, effectiveness of mitigation activities, and effort spent for the risk management.
-------
Areas of risk managementAs applied to corporate finance, risk management is the technique for measuring, monitoring and controlling the financial or operational risk on a firm's balance sheet.
The Basel II framework breaks risks into market risk (price risk), credit risk and operational risk and also specifies methods for calculating capital requirements for each of these components.
Enterprise risk management In enterprise risk management, a risk is defined as a possible event or circumstance that can have negative influences on the Enterprise in question. Its impact can be on the very existence, the resources (human and capital), the products and services, or the customers of the enterprise, as well as external impacts on society, markets, or the environment. In a financial institution, enterprise risk management is normally thought of as the combination of credit risk, interest rate risk or asset liability management, market risk, and operational risk.
In the more general case, every probable risk can have a preformulated plan to deal with its possible consequences (to ensure contingency if the risk becomes a liability).
From the information above and the average cost per employee over time, or cost accrual ratio, a project manager can estimate
- the cost associated with the risk if it arises, estimated by multiplying employee costs per unit time by the estimated time lost (cost impact, C where C = cost accrual ratio * S).
- the probable increase in time associated with a risk (schedule variance due to risk, Rs where Rs = P * S):
- Sorting on this value puts the highest risks to the schedule first. This is intended to cause the greatest risks to the project to be attempted first so that risk is minimized as quickly as possible.
- This is slightly misleading as schedule variances with a large P and small S and vice versa are not equivalent. (The risk of the RMS Titanic sinking vs. the passengers' meals being served at slightly the wrong time).
- the probable increase in cost associated with a risk (cost variance due to risk, Rc where Rc = P*C = P*CAR*S = P*S*CAR)
- sorting on this value puts the highest risks to the budget first.
- see concerns about schedule variance as this is a function of it, as illustrated in the equation above.
Risk in a project or process can be due either to Special Cause Variation or Common Cause Variation and requires appropriate treatment. That is to re-iterate the concern about extremal cases not being equivalent in the list immediately above.
Risk management activities as applied to project management
In project management, risk management includes the following activities:
- Planning how risk management will be held in the particular project. Plan should include risk management tasks, responsibilities, activities and budget.
- Assigning a risk officer - a team member other than a project manager who is responsible for foreseeing potential project problems. Typical characteristic of risk officer is a healthy skepticism.
- Maintaining live project risk database. Each risk should have the following attributes: opening date, title, short description, probability and importance. Optionally a risk may have an assigned person responsible for its resolution and a date by which the risk must be resolved.
- Creating anonymous risk reporting channel. Each team member should have possibility to report risk that he foresees in the project.
- Preparing mitigation plans for risks that are chosen to be mitigated. The purpose of the mitigation plan is to describe how this particular risk will be handled – what, when, by who and how will it be done to avoid it or minimize consequences if it becomes a liability.
- Summarizing planned and faced risks, effectiveness of mitigation activities, and effort spent for the risk management.
------
LimitationsIf risks are improperly assessed and prioritized, time can be wasted in dealing with risk of losses that are not likely to occur. Spending too much time assessing and managing unlikely risks can divert resources that could be used more profitably. Unlikely events do occur but if the risk is unlikely enough to occur it may be better to simply retain the risk and deal with the result if the loss does in fact occur.
Prioritizing too highly the risk management processes could keep an organization from ever completing a project or even getting started. This is especially true if other work is suspended until the risk management process is considered complete.
It is also important to keep in mind the distinction between risk and uncertainty. Risk can be measured by impacts x probability.